Original Estimate and actual estimate fields seems to be gone when adding a task or issue, how can i get those fields back in again?

Romy Mathew September 7, 2015
 

1 answer

1 vote
Pilar
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 7, 2015

Add the field time tracking to the create issue screen for your project,

Also check if time tracking is turned on.

Also check if you have the time tracking permissions in the permission scheme.