Not update past story count or story point data in chart board

Atlassian JIRA (v4.4.4#664-r167664) & GreenHopper (v5.8.4)
Is it possible to prevent the chart board from update story count or story points for days that have already been past. This will give a better visual cue of what is happening during the sprint/iteration.
For example, on day 1, my sprint has 5 stories. On days 2, one story is moved to done. On day 3, team adds 1 new story to the sprint. On day 4, team moves two more stories to done. On day 5, team adds one new story. I would like to see the desired story burndown instead of the actual shown in the chart below. Same question for CFD.
Burndown chart from Greenhopper
Desired CFD.
CFD chart from Greenhopper.

2 answers

1 accepted

0 votes
Renjith Pillai Community Champion Jan 19, 2013

Can you try the new Rapid boards? I am guessing that it is much more stricter on the values picked up based on the entry values into the Sprint.

Look like Jira v5.2.6/Greenhopper 6.2.2.2 fixes this.

I'm having exactly the same problem. Could you explain, what you exactly did to make it work, please? I'm using the Classic Issue Burndown Chart with Jira v.5.2.5 and Greenhopper 6.2.2.2. I would be surprised if a Jira upgrade to v5.2.6 would help?!

I'm using the new Scrum Board in Jira Agile (6.3). There are a couple additional fixes in 6.3.2.2 that you will want.

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

246 views 0 11
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot