I'm using Next Gen Kanban and adding child issues to each story. These child issues become Sub-tasks. When I review the board, however, only the story is showing up on the board. I can filter by task and story, but not sub-task. Since a sub-task may be picked up my multiple team members, how do I monitor sub-task progress on a board?
Hello @Dylan Higgins
Welcome to the community.
You should be able to use the Group By option to select Sub-task, and then you will see each subtask as a card.