I am curious if you plan to support multiple sprint in the Rapid Board. We have many projects, but I seem to be able to only build 1 sprint into 1 project at a time. I may have multiple sprints underway at the same time within the same project, based on available resources, but it seems like the Rapid Board can only deal with 1 sprint at a time.
I understand I could completely alter my project set up, but I feel like the reporting would be completely invalidated.
Any thoughts?
With the release of Parallel Sprints the answer is that you can now run more than one sprint at a time on a single board.
This answer is not entirely correct. You can only start a sprint on a board if none of the issues matched by the filter are currently in a sprint. You must carefully slice your issues by filter so that there will not be any overlap.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kenneth,
you can create multiple rapid boards based on different search filters. Then you can start a new sprint with each rapid board.
Cheers
Thomas