I have two projects which are to be implemented by one team. Have created backlogs for each project. For sprint planning I want for instance I active sprint to pull issues from both projects. Or initially create a backlog for both projects. I can not find a solution for that. That is why I had to create two active sprint sprints for the the two projects.
Thanks
Ivo
Sprints and backlogs belong to boards, not projects.
All you need to do here is create a new Scrum board that has a board filter like "Project in (ABC, DEF)" so it looks at both projects. So it can then attach a backlog and sprint to them in one go.
there is another exotic solution.
you can work with backlogs separately and create two active sprints and than create a board where use filter like "project in (A, B) and sprint in openSprints ()"
such approach will give you the opportunity to work with backlogs separately in case you have not the same person in a role of PO for example. SO it might have some benefit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.