Manage estimates after a forecast phase

Hi there,

We are using Jira both for strategic planification of our projects and operational.

We have a dedicated Jira project where we store each project as a Jira Issue with a subtask for each Team that we be impacted by the project.
Each subtask have high level estimate, to have a first view, very high level, on a our capacity planning for the coming year.
It helps us build our portfolio and start conversation where it seems we will have some risk regarding capacity.

Once validated, each Project Manager start to work on spliting the activities with the teams involved.

In order to enforce good practices and data quality, we would like that each activity link to a project for a specific team, when estimated, decrease the amount of estimates for that specific team and project that is stored in the subtask previously mentionned.

So that we keep project estimation aligned with the forecast. 

It could be done manually, but if any of you have any recomendation, advice or experience with such a practice, thank you for sharing !

 

 

 

0 answers

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
SERVER
TAGS
Community showcase
Published in Jira Software

An update on Jira Software customer feedback – June 2022

Hello Atlassian Community! Feedback from customers like you has helped us shape and improve Jira Software. As Head of Product, Jira Software, I wanted to take this opportunity to share an update on...

5,008 views 18 31
Read article

Atlassian Community Events