In the review session, stories that are complete are moved from "Resolved" to "Done" as per acceptance from the Product Owner. All tasks (where relevant) are closed, all acceptance criteria are checked and completed. However, when the Sprint is closed, all the stories in the last column "Done" are not closed and only carried forward to the new Sprint.
My board is configured as follows:
What can I do so that the stories that are moved to the last column "Done" will be closed when the Sprint is closed?
Hi @Riaan Nel and welcome to the community!
I would make sure that the workflow enforces a resolution is set when the issue transitions to Done.