Jira, Burndown Chart for Tasks that are split between multiple teams

Wojciech Cora April 14, 2021

Hi! 

1. On one Epic work two teams. This is how the Tasks are split. 

How to create burndown charts that report progress for this two teams working on the same Epic?

2. Is there a chance to make chart with burndown of Epics?

 

Thanks

Wojciech 

2 answers

0 votes
Wojciech Cora April 15, 2021

Thanks Alexander, this is what I did but for some reason the line is flat (our tasks have no estimates in story points but in hours. ) it depicts progress on the horizontal line but the vertical values are 0 throught the whole sprint. And epics burn down chart is anavailable for some reason...

Alexander Pappert
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 15, 2021

sorry I could not help you

0 votes
Alexander Pappert
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 14, 2021

https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-epic-burndown-report/

the burndown chart is for the complete sprint and inculdes all epics, stories, ...

maybe if you create a board for each team with a filter that only includes only this team issues