Jira Aging Backlog Report

Is there a way in Jira to show all issues in the backlog that have aged beyond a certain point (ex. 6 weeks)?   We would like to ensure that our teams' backlogs remain fresh and relevant, and are thinking about purging older issues.

1 answer

0 votes
Jack Brickey Community Champion Aug 22, 2017

try this filter.

project = ABC and status != done and sprint is empty and createddate <= -6w

you may have to tweak a bit to meet your needs

if you want to view in backlog you should be able to simply create a quickfilter --> createddate <= -6w

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Statuspage

Introducing Statuspage Getting Started guides! First up: What is Statuspage?

Over the next several weeks we'll be sharing some of our Getting Started guides here in the community. Throughout this series of posts, we'd love to hear from customers and non-customers ab...

36 views 2 1
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you