The epics panel in JIRA Agile planning only seems to support up to 9 epics displayed. Is there any way this can be changed?

JIRA 6.0.7

JIRA Agile 6.3.13.0

1 answer

1 accepted

1 vote
Answer accepted
Anna Cardino
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 30, 2014

Hello Daan,

As fas I know, there shouldn't be a limit to the number of epics showing in the panel. I hav tried it on my instance and I was able to see more than 9 epics on the panel.

That's so strange. I would encourage you to create a support ticket on support.atlassian.comso you can provide a screenshot of the UI that you are seeing. Our support enginners will be more than happy to help you.

Regards,

Monique

Daan Timmer June 15, 2014

It was my colleagues fault... He had been setting epics to 'done' whilst they were not. Thing is, it is quite difficult to see which epics are marked as 'done' because it is nowhere listed. I had to edit the Issue views in order to make the 'marked as done' field visible, edit them and hide the field again.