Our team is new to JIRA. We are using it to do our AGILE sprints. Right now it appears we are able to start a new sprint before we close the previous one. Shouldn't JIRA at least give us some sort of flag letting us know we should close the previous sprint before starting a new one? Just wanted to see what the expected behavior for this is.

1 answer

1 accepted

That's a feature of Jira Agile(it is not enabled by default). You can enable/disable it in the Add/ons administration tab, the setting is found in JIRA Agile Labs under the name Parallel Sprints.

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

661 views 4 15
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot