JIRA Agile - Edit Sprint End Date

Shelli November 26, 2015

Is it possible to edit a sprint end date?

1 answer

1 accepted

1 vote
Answer accepted
GabrielleJ
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 26, 2015

Yes you can. If you have the correct project/board permissions, Go to your Agile Board, switch to the "Plan" view then hover over the Sprint End Date (the second date you can see right below the Sprint name) which will bring up the Pencil Icon for editing.

Reference: https://confluence.atlassian.com/agile/jira-agile-resources/jira-agile-faq/what-are-the-permissions-used-in-agile-boards

Shelli November 26, 2015

Thanks. It's the "Backlog" tab in the version I have for future reference for others.

GabrielleJ
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 26, 2015

Oh ok :) Thanks for pointing that out!