JIRA Agile - Edit Sprint End Date

Is it possible to edit a sprint end date?

1 answer

1 accepted

Yes you can. If you have the correct project/board permissions, Go to your Agile Board, switch to the "Plan" view then hover over the Sprint End Date (the second date you can see right below the Sprint name) which will bring up the Pencil Icon for editing.

Reference: https://confluence.atlassian.com/agile/jira-agile-resources/jira-agile-faq/what-are-the-permissions-used-in-agile-boards

Thanks. It's the "Backlog" tab in the version I have for future reference for others.

Oh ok :) Thanks for pointing that out!

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Feb 26, 2019 in Jira Software

How to prevent the propagation of unused project schemes, workflows & screens in Jira software

Atlassian ranks project attributes as the third most important factor impacting performance in the category of data. It’s not surprising, since project attributes are precisely the rules used to ma...

626 views 0 7
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you