JIRA Agile - Edit Sprint End Date

Is it possible to edit a sprint end date?

1 answer

1 accepted

Yes you can. If you have the correct project/board permissions, Go to your Agile Board, switch to the "Plan" view then hover over the Sprint End Date (the second date you can see right below the Sprint name) which will bring up the Pencil Icon for editing.

Reference: https://confluence.atlassian.com/agile/jira-agile-resources/jira-agile-faq/what-are-the-permissions-used-in-agile-boards

Thanks. It's the "Backlog" tab in the version I have for future reference for others.

Oh ok :) Thanks for pointing that out!

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published May 21, 2018 in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

1,253 views 10 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you