Item concluído voltou para o backlog

Vivian Junqueira December 6, 2021

oi... precisava de uma ajuda, por favor...

encerrei uma sprint e os itens concluídos voltaram para o backlog, mas com o status concluído.

Isso nunca tinha acontecido, como faço para alterar?

2 answers

1 vote
Niranjan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 6, 2021

Hi @Vivian Junqueira ,

JIRA Software does not display issues from the last column of the Scrum board configuration in the backlog section. If your closed issues are not mapped to the last column of the board, then they would be displayed in the backlog.

https://confluence.atlassian.com/jirakb/closed-or-resolved-issues-appear-in-a-scrum-board-backlog-in-jira-server-779159078.html

0 votes
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 6, 2021

You need to ensure all done items are in the right most column of the board at the time of sprint completion 

Roberta Guimarães de Souza March 12, 2024

I have the same problem as @Vivian Junqueira . Even though cards are marked as concluded and placed in the last kanban column, they keep coming back to the next sprint in the backlog.

 

Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 12, 2024

Are the issues Stories/tasks include subtasks that are incomplete possibly? 