Issues being marked Done when moved to a Sprint even though it isn't Done.

We have a problem where issues are getting their resolution marked to Done when they get moved into a sprint.  Ideally the Resolution field would only get updated when an issue moves to the Awaiting Publish or Published phases of the workflow.  Is there a reason they are being changed incorrectly?  

1 answer

1 accepted

0 vote

There are several ways to do this, but in most cases, you have

  • Used the workflow configuration option in a "simplified workflow" to say "this status should be configured to be 'done'"
  • Put a post-function on the workflow that sets it
  • Put the resolution on the transition that moves them into the sprint
  • Scripted a listener to catch the move into sprint and set the resolution
  • Set up an Automation to do the same

Thank you so much!

Suggest an answer

Log in or Join to answer
Community showcase
Emilee Spencer
Published Friday in Marketplace Apps

Marketplace Spotlight: DeepAffects

Hello Atlassian Community! My name is Emilee, and I’m a Product Marketing Manager for the Marketplace team. Starting with this post, I'm kicking off a monthly series of Spotlights to highlight Ma...

56 views 0 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot