Is there any way to know the user log of work of the current sprint?

Ricard Marí January 15, 2013

One of the team KPI is the log of work / available team capacity.

The purposes of this KPI is evangelist team to the tool (GreenHopper) and the agile process.

Actually we're using the Burndown Chart report to extract the "Log Of work" of the team, but is a manual process.

Is there any way to know the log of work of the team (or every team member) of the current sprint? Any Report or similar tool? Or any way to export this information?

Thank you

2 answers

0 votes
Renjith Pillai
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 16, 2013

If you create a board per team, which filters the issues valid for them, doesn't the burn down chart show only the values for the team?

Ricard Marí January 16, 2013

Yeap, this is what we did for the moment! But is a manual revision, because the Burn Down Chart report doesn't allow to export to excel the list of rows for example. Thanks

0 votes
Neil Padgen January 15, 2013
Ricard Marí January 15, 2013

We'll try the trial to check it! Thank you!

Ricard Marí January 16, 2013

We discarted the plug-in, is not integrated with Greenhopper. Regards