Sprint cycle is fixed in our project and we want to defne start and end dates of 2-3 upcoming sprints so that testers are aware when are their fixes scheduled... is there any way I could set start/end date of the upcoming sprints.
You cannot do that before the sprint is about to start. What you can do is to "link" 1 sprint to 1 version. Then you can specify expected dates for future versions, e.g. future sprints. We are doing this, and it doesn't add any overhead as we also use found in version/fix version fields in Jira (in addition to sprints/Jira Agile.