Is there a way to sync Story Points and Original Estimates?

Lewis Foster May 9, 2012

We're just getting started with GH and don't see the why Story Points should differ from the Original Estimate in days.

Is there a way to sync the two or to copy from Story Points to Original Estimate (or vice versa?)?

All our features have had their original estimates filled in by developers but when it comes to planning, I can't see these values on the Rapid Board. It would be fantastic if I could toggle from "Story Points" to "Original Estimate (days)"

1 answer

1 accepted

0 votes
Answer accepted
sclowes
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 10, 2012

The next version of GreenHopper (5.9.7) which will be out in the next couple of days will allow you to choose Original Estimate for your estimation statistic.

Thanks,
Shaun

Suggest an answer

Log in or Sign up to answer