Is there a way to sync Story Points and Original Estimates?

We're just getting started with GH and don't see the why Story Points should differ from the Original Estimate in days.

Is there a way to sync the two or to copy from Story Points to Original Estimate (or vice versa?)?

All our features have had their original estimates filled in by developers but when it comes to planning, I can't see these values on the Rapid Board. It would be fantastic if I could toggle from "Story Points" to "Original Estimate (days)"

1 answer

1 accepted

The next version of GreenHopper (5.9.7) which will be out in the next couple of days will allow you to choose Original Estimate for your estimation statistic.

Thanks,
Shaun

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Feb 26, 2019 in Jira Software

How to prevent the propagation of unused project schemes, workflows & screens in Jira software

Atlassian ranks project attributes as the third most important factor impacting performance in the category of data. It’s not surprising, since project attributes are precisely the rules used to ma...

668 views 1 8
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you