Is there a way to sync Story Points and Original Estimates?

We're just getting started with GH and don't see the why Story Points should differ from the Original Estimate in days.

Is there a way to sync the two or to copy from Story Points to Original Estimate (or vice versa?)?

All our features have had their original estimates filled in by developers but when it comes to planning, I can't see these values on the Rapid Board. It would be fantastic if I could toggle from "Story Points" to "Original Estimate (days)"

1 answer

1 accepted

The next version of GreenHopper (5.9.7) which will be out in the next couple of days will allow you to choose Original Estimate for your estimation statistic.

Thanks,
Shaun

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Mar 28, 2018 in Jira Software

Can a company’s culture make or break agile adoption?

Can a new-to-agile team survive and thrive in a non-agile culture? If so, what advice would you give to those trying to be agile in a non-agile culture? What's the key(s) to success? Share your thoug...

17,625 views 18 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you