Is there a way to do sub-task estimation rollup?

Chris Tooley September 3, 2012

We don't do any estimates based on time. All of our estimates/actuals are based on Story Points. So, when we start grooming our backlog we estimate all of our Story issues with a Story Point value. As those Stories get put into a Sprint we do task breakout. To accurately reflect partially completed Stories we assign Story Point values to the Sub-Task issues. The problem with this is that in the Chart Board and various Dashboard graphs, we can either have sizes on the Sub-Tasks or Stories, but not both due to cumulative rollup, but as far as I can find, the Rapidboard doesn't do that.

Any hints?

3 answers

1 accepted

0 votes
Answer accepted
cgauterio
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 13, 2012

Hi Chris,

You are correct, the sub-tasks (or their estimations) are not displayed on the Rapid Board, plan mode specially.

There is an improvement request regarding it being tracked at GHS-5614. Please add yourself as a watcher to be notified of future updates.

Cheers,

Clarissa Gautério

Atlassian Support

0 votes
sclowes
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 18, 2012

Hi Chris,

There's not currently an easy way to model partial burndown of Story Points. The easiest alternative would be to use hours where 1h = 1point. You can then do what you're looking to do.

Thanks,
Shaun

Ivar
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 21, 2013

We've been working hard for years to get away from the use of hours. You yourself state in the blog that

A story point approach based on original estimates can deliver the answers to these questions without the anxiety around ‘accuracy’ that teams feel when asked to estimate in hours.

So we've been estimating sub-tasks in story points. Now you want us to revert to hours again?

https://answers.atlassian.com/questions/203746/rapid-board-story-points-and-sub-tasks-aggregate-estimates-up

Like # people like this
John Gill May 30, 2018

Why can't you up-vote replies! If I could Ivar gets my up-vote!

0 votes
Renjith Pillai
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 17, 2012

Probably it's a concept issue here, as story points are at story level and technical tasks are estimated in hours during the sprint planning. This is the reason why this aggregation is not done. At the same time, if estimation is based on Orginal estimate, the sum of the values of the estimate is shown in the Detail view of the issue.

Suggest an answer

Log in or Sign up to answer