Is there a way to Baseline in Greenhopper at the start of a Sprint?

I want to be able to baseline at the start of a sprint or release, so I can show I can track changes and when they occurred, in Greehopper

1 answer

1 accepted

0 votes
Answer accepted

This can be done easily enough by creating a JQL search against the update field using > sprint start date. Show this saved filter on yoru dashboard updating every 15 minutes and you will be able to track things easily.

This won't work because if you resolve a ticket that was in your baseline it would show in your JQL because the update field just changed. Thanks though for the thought. I was hoping to avaid writing a JQL program to do this.

Without JQL I would have a lot more open issues! It's really not too bad. To help underatandinf take a "simple" JIRA query and just cloick the advanced optin, it now translates your simple query into JQL.

Most things can be filtered out in JQL. E.g. in the case you just mentioned one would add

status != resolved

Feel free to give more details and I could help working up a custom JQL query if you like.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Feb 26, 2019 in Jira Software

How to prevent the propagation of unused project schemes, workflows & screens in Jira software

Atlassian ranks project attributes as the third most important factor impacting performance in the category of data. It’s not surprising, since project attributes are precisely the rules used to ma...

607 views 0 7
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you