Is it possible to see each developer's time allocation based sub-task time estimates DURING sprint planning?

Travis Millman September 23, 2012

Our team would like to be able to view a running total of each developer's hours WHILE we are planning a sprint. An ideal solution would be a widget for the right hand side of the planning board that calculates each developer's allocated time for the sprint being planned. Is this possible? Any recommendations for avoiding having to run a hand calculated hours tally alongside? Is there a different way to think about planning you'd like to recommend? Many thanks in advance for any assistance!

1 answer

1 vote
sclowes
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 24, 2012

You might like to try adding a quick filter for each of your developers. You can then apply the quick filter and see the sum of the hours on the sprint footer for each developer. In 6.0.3 the sprint footer shows the sum of both the estimate and the remaining hours (if time tracking is on).

Thanks,
Shaun