Is it possible to list all issues assigned to a Sprint other than the current Sprint?

dave_at_clearbox October 7, 2013

Currently I can filter all issues for the current or past Sprints using a filter string like:

Project = "Project Name" and Sprint = 11

However we have Sprints which haven't started yet and I would like to filter issues assigned to those Sprints and produce reports on their details. This cannot be done because Sprint = 12 does not exist even though it is defined in the Agile Plan view.

3 answers

0 votes
Justin Leader
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 9, 2013
0 votes
Justin Leader
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 9, 2013

This just got implemented, right? In one of the latest JIRA Agile versions?

0 votes
tier-0 grump
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 9, 2013

Odd, I've just tested this - I created some sprints in plan view, dragged some issues into them, left the sprints not started and am able to search for issues in those sprints.

dave_at_clearbox October 9, 2013

Thanks for looking into it. Can you filter all issues based on the unstarted sprints? Can you give an example filter string?