Incomplete issues moved to backlog instead of the new sprint

Ikem Abellon January 14, 2021

Hello Atlassian Community,

I would like to ask for your help regarding the Sprint of one of our customers. When they closed the current sprint it had the option to move the 94 incomplete issues to the new sprint - which is the correct behavior.Sprint.png

However the 94 issues where moved to backlog rather than the new sprints. 

Would like to inquire your expertise on why this behavior occurred? The current sprint is running in parallel with other sprints in the project.

Your help is highly appreciated.

 

Thanks,
Michael

2 answers

0 votes
Daniel Ebers
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 16, 2021

Hi @Ikem Abellon

just for a short clarification: did you mean they selected "PIP-NSW-Q1_2021" to roll the 94 issues over (which was the initial intentions) but instead and despite displaying the "target" sprint in dropdown those 94 ones were sent to the backlog?

Is this correctly understood?

Regards,
Daniel

Ikem Abellon January 18, 2021

Hi @Daniel Ebers ,

Yes that is correct. Instead of rolling into "PIP-NSW-Q1_2021" they are rolled into backlog.

Thanks,
Ikem

Daniel Ebers
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 18, 2021

Quite strange behaviour. Do you have the option in this window to select a different sprint also (so it is "highlighted") and then coming back to the desired sprint?
Maybe it is only some thing of browser not focusing the selection right?

0 votes
Benjamin
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 15, 2021

HI @Ikem Abellon : In order to select another sprint to move the issues go into. There should be one that hasn't started. I'm not aware of option popping up to send tickets to an actively ongoing sprint when closing a sprint. 

 

Hope this helps.