After reviewing our Epics we realized that we want to create a new Project "A" but move/copy a portion of the Epics, its associate Stories and Tasks that currently exist in Project "B".

Is there a way to do this?  have you have done this?

 

Thank

Dwight

 

1 answer

1 vote
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 2, 2019

I while I have not tried this I doubt that the relationship between epics and tasks will remain. Here is what I would suggest.

  1. create the new project
  2. use bulk move to move all tasks under one epic to new project.
  3. create new epic and bulk edit the issue to add epic link to new epic
  4. repeat as required