In Jira Agile, can you setup Dependencies between stories?

Is there a way to setup Dependencies between stories in Jira Agile? So that you can tell if Story A has to be done before Story B.

1 answer

In the Agile methodology, a Story should follow the INVEST mnemonic and should aim to be as independant as possible. Now, if that is impossible, the order of the product backlog should give you the dependencies you need. If A has to be done before B, then A should be higher than B. Finally, if you really looking for a way to mark that dependency, you could use the JIRA issue link function.

But ordering stories in the backlog won't help you manage dependencies if you have many developers working independently.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 29, 2019 in Jira Software

Transforming Jira Software projects for general project management purposes

...It's true that there are projects in Jira; but they are merely a way to cut off issues, to tell them apart from other sections of work and to apply rules that are specific to that team (the schemes)....

187 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you