I am in a chick an egg scenario and cannot assign plan teams to a sprint

Neil Wills May 11, 2023

Issues:

 

My board is configured so the Backlog view excludes initiatives and themes

 

The Advanced roadmap can be pointed to the board view or project view, board view does not work as an input source as it removes the themes and initiatives that I plan to use in the roadmap hierarchy.

Selecting the project view means I dont have the sprints to assign to plan teams

1 answer

1 accepted

1 vote
Answer accepted
Walter Buggenhout
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 11, 2023

Hi @Neil Wills,

You can add multiple issue sources to a single plan in Advanced Roadmaps. So use the board as an issue source for your actual work (the epics and the issues below the epics) and add an additional source (that you can base off a saved filter) to add your initiatives and themes. That way you should get both chicken and eggs in the basket!

Hope this helps! 

Neil Wills May 26, 2023

solved it