Hi friends , Need your help .
I will start to describe my problem -
- I have Project A , Project B & Project C .
- Project C is group which supply features to Project A & Project B .
- Project C have bugs which related to Project A / Project B but under the domain of Project C
- fix version for each bug is always of Project A / Project B (Project C doesn`t have its own versions as it is actually part of Project A/B)
My current solution :
- All Projects open new issues (Story / Bug) under Project C but set Epic link to Epic in their project . In this way Epic received the real fix version .
- All issues are opened to Project C BKL.
- This enable Project C to decide what to take for next sprint and priortize its BKL from all products.
My problem -
- In order to work on bug , user must fill "Fix Version" field (meaning what is the target version of this bug).
- In Jira fix version is taken from current project and therefore Project C can` see the fix version of Project A / B.
Is there option that Project will be "familar" with other projects fix versions ?
What can I do ? I am open for new solutions .
My main aim is to enable Project C to manage 1 sprint and ability to control its BKL .
Thanks in advance .