I just exported the issues in my Jira Software Project in order to create dashboards using Power BI, but I found two differente fields for Original Estimate (Original Estimate and Σ Original Estimate) and also for Remaining Estimate (Remaining Estimate and Σ Remaining Estimate). As you can see, there are two collumns with small differences in the tiltes, but also the data in the filed are different for some issues. My questions are:
1 - Which are the differences between the fields Original Estimate and Σ Original Estimate?
2 - Which are the differences between the fields emaining Estimate and Σ Remaining Estimate?
MArco Camara
The original and remaining estimate fields are actually aspects of the same field, but:
Same sum is done for the remaining fields.
Note that this does not apply to Epics, stories are not sub-tasks of Epics
Thanks Nic, very usefull the information you provided. I am proceeding with my project.
Marco Camara