How to configure Agile SCRUM Board to have Epics, Stories and Tasks?

Ike Garrow December 10, 2014

I need to setup the following hierarchy on the SCRUM board

EPICS --1-to-many-->STORIES--1-to-many–> TASKS

I want/need tasks to appear in backlog for estimation.

PROBLEM:

I have this setup now but TASKS cannot be estimated.

1 answer

0 votes
Dave Theodore [Coyote Creek Consulting]
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 10, 2014

You'll need to add the "Story Points" custom field to the associated screens for the Task issue type or modify the Story Points field contect to allow Task issue type to use it.