How to configure Agile SCRUM Board to have Epics, Stories and Tasks?

I need to setup the following hierarchy on the SCRUM board

EPICS --1-to-many-->STORIES--1-to-many–> TASKS

I want/need tasks to appear in backlog for estimation.

PROBLEM:

I have this setup now but TASKS cannot be estimated.

1 answer

You'll need to add the "Story Points" custom field to the associated screens for the Task issue type or modify the Story Points field contect to allow Task issue type to use it.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Monday in Jira Service Desk

Frequently Asked Questions for Jira Service Desk (AKA JSD FAQ)

Just the FAQs! Welcome to the Community, and this Focused-FAQ! Here, we've pulled together some of the most frequently asked questions associated with Jira Service Desk (JSD). We hope ...

124 views 0 11
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you