How to close a sprint with cancelled tasks

Alex Viale January 2, 2020

Unable to close sprints that have cancelled tasks. 

1 answer

0 votes
Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 3, 2020

Hello Alex,

Thank you for reaching out to Atlassian Community!

When closing a sprint, the completed tickets are the ones mapped to the very last column, that's why it's not possible to close the sprint with canceled tasks.

There is a feature request suggesting the implementation of this ability:

Please, click on vote and watch to receive updates about the feature.

Regards,
Angélica

Alex Viale January 3, 2020

:) So what should i do to close a sprint in this case?

Like # people like this
Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 6, 2020

Jira considers as completed all issues mapped to the very last column, so you need to map the statuses to the last column in order to close the sprint.

Like Boudewijn Sjouke likes this
Alex Viale May 6, 2021

Mapping it to the last column would just not be accurate. The last column would never be "cancelled". I must be missing something

Like Valentin Dragin likes this
Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 7, 2021

Hi Alex,

On next-gen (team-managed) projects currently, only the last column sets a resolution and a ticket is considered Resolved if it has a resolution.

It’s possible to edit the workflow now, but still, only the very last column on the board is what will set the resolution.

Valentin Dragin June 17, 2021

Much wow,

very cool. 

Like Deleted user likes this