How to Automate Over Due days field ?

Yash Raj May 23, 2022

Hello everyone,

Here I have a start date and end date of a particular subtask

and also the dates on which the particular subtask is completed 

if you in the example screenshot

in the task is over due by 1 day, this i want to automate

Need to enter the difference of end date and ended date in the over due days field

kindly help

Thanks

YashOver due.PNG 

3 answers

1 accepted

0 votes
Answer accepted
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 23, 2022

Hi @Yash Raj 

I assume the Over Due Days field is a custom number field - is that correct?

I would create a scheduled Automation rule to run once a day or however often you want it to run.

Add a condition for status != Done

Then do an Edit Issue action to update the custom number Over Due Days field. 

Then in the box for the field value, put in something like: 

{{issue.customfield_17354.diff(now).days}}

Where the custom field is the End date field you are using. 

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 23, 2022

Hi @Yash Raj 

Yes, and...to John's answer:

Your example seems to show planned Start and End Date and actual Start and End Date.  Is that correct?  If so, you would need to perform that date difference twice for the different pairs of date fields, and then subtract to find the over due days.

Kind regards,
Bill

Like Yash Raj likes this
Yash Raj May 23, 2022

Hi @John Funk 

i have tried with your given automation rule

and its comparing the custom field date to todays date and its showing "0" days in Due days field

but i want to compare the actual start and end and if its excides the "No of day to complete" then it should show, how many days it has over due 

Thanks

Yash

Yash Raj May 23, 2022

This "Number of days to complete" value should minus with the actual start and end 

so that we can see how many days it has dueDue.PNG

Yash Raj May 24, 2022

Hi @Bill Sheboy 

You are correct

But how to get difference of actual start and end date minus no. of days to complete 

John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 24, 2022

Maybe you could do two different diffs on the dates with results going to two different custom number fields. And then do a a subtraction formula to place the value in a third custom number field. 

Like # people like this
Yash Raj May 24, 2022

Any example please

Yash Raj May 25, 2022

Hi @John Funk @Bill Sheboy 

As per the solution given by you

i have created another number field in which the differnence of the 2 dates is been updating, but the issue here is "its calculation the days but we need the Business days to calculate in the field.

 

another thing as i mention, i want to see the Due days 

for that i have made an automation to edit the Due days field with calculation of

{{issue.fields.Diff.CESD/CEDD.minus(No of days to complete).days}}

it shows it success but no output to be seen

 

Now the first issue is

1. It should Calculate Business days Instead of days

2. Subtraction of two field is not working

 

kindly help me with thisCapture.PNGCapture1.PNGCapture4.PNG

Yash Raj May 26, 2022

1. It should Calculate Business days Instead of days

is solved now

i have have mention "BusinessDays"instead of days in the smart value

{{issue.customfield_13578.diff(issue.customfield_13579).BusinessDays}}

Like # people like this
Yash Raj May 26, 2022

2. Subtraction of two field is not working

 

now this also solved

Thanks for support guys

Like # people like this
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 26, 2022

Great! Glad this is working for you now. 

Like Yash Raj likes this
0 votes
Yash Raj June 24, 2022

Hi @John Funk @Bill Sheboy 

Hope you both doing well

as the above solution 

same i want to implement in the parent task

am able to get the difference of two fields dates but not able to subtract with the "No of days to complete" field.

 

and second thing
i have created the subtask automation with field values and at the same time i have to fill the task field as well..

kindly suggest how to do it

Regards

Yash

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 24, 2022

Hi @Yash Raj 

Please post images of your rule, and the audit log details when you have a question, including what is not working as you expect.  That will provide context for the community to offer suggestions.  Thanks!

For example, what is different for subtracting the other field using the same methods you have already implemented?

Kind regards,
Bill

0 votes
Yash Raj May 23, 2022

,

Suggest an answer

Log in or Sign up to answer