How do you configure tempo planner outlook integration to ignore events of type "working elsewhere"

Kristjan Hoareau December 15, 2022

We use outlook integration, so our project managers can get a better estimation of people availability based on their events in outlook.

When users have an event of type "working elsewhere" in their outlook, tempo counts their hours as busy even though that is not true.

Can you configure tempo planner to ignore this kind of events?

1 answer

0 votes
Tempo Support
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 15, 2022

Hello Kristjan,

Thank you for contacting Tempo Support,

At the moment, Planner does not feature to restrict certain events. However, since your use case is valuable to us, 

We encourage you to place a feature request in our idea portal for our Product team to consider adding this in the future.
Here is a document with links to the portal and an explanation of how it works:
Tempo Idea Portal
Best Regards,

Steven

Tempo Support Team

Kristjan Hoareau December 16, 2022

thanks for a quick reply.
I created the feature request here: https://ideas.tempo.io/ideas/T-I-2101

 

Br,

Kristjan