How do I filter estimate in Plan view of current sprint?

Hi Everyone,

We're using GreenHopper to coordinate the work of a largish team broken down into smaller subteams. We are effectively using filters to independently filter the work for each subteam in Plan and Work views. While we are planning a sprint, the cumulative estimate (at the bottom right of the sprint box) shows the filtered estimate and the unfiltered estimate. This behavior is perfect.

However, once the sprint has started, the estimates reported at the top of the active sprint (in the Plan view) do not respect the current filter. As we progress through our sprint, it is difficult for each subteam to see how much work is left in the active sprint. We can see how much work is left for the entire team, but the remaining estimate for the subteam requires summing the filtered issue estimates by hand.

Is this a known issue, or are we using the tool incorrectly?

Thanks for any help,

Preston Jackson

1 answer

1 accepted

2 votes
Answer accepted

I don't think this functionality exists currently. There is a similar question here: https://answers.atlassian.com/questions/116803/showing-time-remaining-and-quick-filters

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Feb 26, 2019 in Jira Software

How to prevent the propagation of unused project schemes, workflows & screens in Jira software

Atlassian ranks project attributes as the third most important factor impacting performance in the category of data. It’s not surprising, since project attributes are precisely the rules used to ma...

577 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you