We are running Jira Agile, but have some projects that were in the system before we started using it. I want to see the tasks in those older projects on the new Agile board.
I found this thread, but it lacked specific steps that need to be taken.
https://answers.atlassian.com/questions/205345/how-do-you-convert-a-jira-project-to-a-jira-agile-project
Particularly, it looks like I need to add the project to the enabled projects list for the plugin. How would I do that? And once that is done, will I be able to group my issues into sprints and look at them on the board?
Here's the answer which someone from Atlassian explained:
1) Go Agile --> Manage Boards.
2) Click Create Board
3) Create Scrum board (which is what I want)
4) Board for existing project
5) Name and select project and hit Create Board.