How do I configure Create SubTask screen?

Lana Decker August 6, 2013

I have 2 types of subtasks - Test tasks and Development tasks.

All I want to see on them is "Assignee", "Acceptance criteria", "Description", "Summary" and hour estimates fields (Log Work). How do i do that?

I was thinking to use " Add Issue Type Screen Scheme " but I can map it to Issue types, not sub tasks...

1 answer

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 6, 2013

Actually, yes, you do use "issue type screen schemes". The screen schemes are there to say "use screen X for purpose Y when using issue type Z". They don't care whether an issue type is a top level issue or a subtask.

When you add a new screen scheme to an issue type screen scheme, you'll find it simply lists all the issue types you have in your system.