How can i set the StartDate in Agile Gadget

Constantin Scheuermann March 13, 2013

Hi there,

i am not able to change the "start Date" within the Agile Gadget. I can choose a earlier Date but as soon as i click Save and Apply my changes are lost. It always selected the current date.

Is there a possibility to change that?

Thanks a lot in advance

Constantin

1 answer

1 accepted

0 votes
Answer accepted
Constantin Scheuermann March 13, 2013

I found the solution. Under Agile -> Calssic view, Expend the Version view and there you can set the StartDate.

Suggest an answer

Log in or Sign up to answer