Hours not shown when planning sprint if over 1000 hours

david.humeniuk@udri.udayton.edu September 3, 2012

I'm trying to use the new upcoming sprint planning feature in Greenhopper. However, when I add enough issues to an upcoming sprint such that the total hours are greater than 1000, the actual value is not displayed.

I'm sure I can work around by starting the sprint and adding/removing issues as needed.

1 answer

1 accepted

0 votes
Answer accepted
Thiago Ribeiro
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 20, 2012

This is a new Bug on GH:

Plan mode not showing sum of hours

Suggest an answer

Log in or Sign up to answer