Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,457,311
Community Members
 
Community Events
176
Community Groups

Hi, how do we update the completed sprint date or remove it from report?

In sprint report I am trying to edit or remove the date from completed sprint?

 

 

1 answer

0 votes

Hello @Rachel Dorthy,

Welcome to Atlassian Community!

In case you are using a company-managed project (classic), in order to edit the end date of a completed sprint, it’s necessary to reopen it first. Then, it will be possible to edit and then, you can complete the sprint again.

For more information, please, check the documentation below:

There is a feature request suggesting to add the option to edit it without reopening the sprint:

If it’s a team-managed project (next-gen), currently, it’s not possible to reopen or delete a completed sprint. There is a suggestion for that as well:

Please, click on vote and also watch the features to receive updates from our product team.

If you have any other questions regarding this matter, please let us know.

Kind regards,
Angélica

Trudy Claspill Community Leader Dec 02, 2022

In case somebody else comes across this post in searches I want to point out that when you reopen a sprint, yes, you can edit the planned end date.

However, the date shown in the Sprint Report is the actual date when the Complete process was executed for the sprint, not the planned end date you manually set.