in the planing view of our scrum board we have planed our next sprints.
At the bottom of each sprint there is a calculation how much time remains for this sprint. Currently this value is shown for example as "10w 3d". We as a team are using days as our basic estimation unit and find the week format a bit confusing - and would instead just use only days, e.g. "53d" in this case.
Is there a way to change this behaviour?
Hi Jan,
In GH 6.0.7 (which will be released shortly), the format of this time will be controlled by the Time Tracking configuration in JIRA (which has three options, pretty, days and hours).
Thanks,
Shaun