Greenhopper planing view change time format from "12w 1d" to "61d"

JanG October 28, 2012

Hello,

in the planing view of our scrum board we have planed our next sprints.

At the bottom of each sprint there is a calculation how much time remains for this sprint. Currently this value is shown for example as "10w 3d". We as a team are using days as our basic estimation unit and find the week format a bit confusing - and would instead just use only days, e.g. "53d" in this case.

Is there a way to change this behaviour?

1 answer

1 vote
sclowes
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 29, 2012

Hi Jan,

In GH 6.0.7 (which will be released shortly), the format of this time will be controlled by the Time Tracking configuration in JIRA (which has three options, pretty, days and hours).

Thanks,
Shaun