GreenHopper Burndown Chart - How to update statistics after the sprint

Situation: Our sprint review is held at the end of the final sprint day. At the sprint review, the Product Owner would take any incomplete stories and move them to the Product Backlog for prioiritization for the following sprint.

Result: The Sprint burndown chart shows that all issues are complete and remaining work is zero. Therefore, it looks like the team has completed all of the stories and tasks as scheduled. We would prefer to have an accurate represenation of the status on the final day. But, the PO also wants to be pro-active in managing the issues for the next sprint.

Question: Is there a way to update/modify the burndown chart to accurately reflect the status on the final day after the sprint is closed?

That is, modify the data so the graph shows the situation as of the final day at 4PM?

1 answer

1 accepted

The way I'd recommend is to use GreenHopper's release function on the planning board. This will open a dialog, showing incomplete stories at that point. You can decide where to move them (in your case, into your backlog). GreenHopper will then record the information on the moved issues that they've been part of the sprint you've just released, and the burndown charts in the released board will reflect this.

Cheers,

Alex

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

973 views 5 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot