One of the teams I have using greenhopper is seeing the burndown chart display as attached. Is there a way to have Greenhopper properly scale the charts for really whacky data like this?

This is running on JIRA 4.4.5 with Greenhopper 5.8.7.

Thanks!

-Sheppe

1 answer

1 accepted

This widget could not be displayed.

Hi,

This is a problem that is experienced by customers using the Chart Board where the burn down actually burns up instead of down (i.e more work is found than resolved).

You might look to look at the Rapid Board (available for Scrum in JIRA 5.0 and GH 5.10.1). The burndown in the Rapid Board does not suffer from this problem.

Thanks,
Shaun

Thanks Shaun, that's all I needed to hear. :)

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Apr 22, 2018 in Jira Software

How-to setup a secured Jira Software 7.9.0 on Ubuntu 16.04.4 in less than 30 minutes

...PermissionsStartOnly=true User=www-data Group=www-data ExecStart=/opt/jira/bin/startup.sh ExecStop=/opt/jira/bin/shutdown.sh TimeoutStartSec=120 TimeoutStopSec=600 PrivateTmp=true [Install] WantedBy...

1,488 views 10 12
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you