In GH6 one of the Estimation Statistics is the original estimate. What happen if an issue is not Done in a sprint? We have a setting that the Original Estimate can not be changed once someone starts loggin work againts an issue (option Legacy Mode for Time Tracking is ON).
For example original estimate for issue A at Sprint 1 was 10 hrs. logged effort was 9 hrs. but the issue was not closed in Sprint 1. For planning the next Sprint I need this issue to have a original estimate of 1 hr. or whatever the value the programmer set for the remaining estimate.
Or maybe I have to turn legacy mode OFF, reset the original estimate, and turn it back ON?
I think the best way should be to have Remaining Estimate as one of the Estimation options for coping with this scenario where an issue is not closed in a sprint and span more than a sprint.
Comments?
That smells a little to me. If we are talking stories then sub tasks should not span sprints. The same should be true of tasks really. A team should only commit to what they think they can achieve in a Sprint.
Realistically of course sometimes things will not be done and there will still be work left on some tasks. I suggest in these hopefully rare cases you could clone the task and manaully complete the original estimate to be the remaining estimate. You could link the 2 JIRA sub-tasks and then close the first 90% done one.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.