Fix Greenhopper Progress color bar

I customized the workflow a bit and created heirarchies within my project to assist with managing the releases. The heirarchy is Project, Sprint, Cycle or Project, Release, Sprint. The kanban project task board progress bar looks like the following:

I want the "In-Progress" and "Mainline" swimlanes to be yellow instead of red. I'm sure the reason the color is incorrect is because I have something incorrectly mapped but I'm not able to find where to make my fix.

1 answer

1 accepted

0 votes
Answer accepted

I've determined that the Greenhopper Progress bar is self updating. In essence, whatever stories are not started or started worked on, the bar will be RED. Those stories that are "in-progress" will be yellow and those completed will be green. Therefore the progress bar is dynamic based on the number of stories in the various states.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Feb 26, 2019 in Jira Software

How to prevent the propagation of unused project schemes, workflows & screens in Jira software

Atlassian ranks project attributes as the third most important factor impacting performance in the category of data. It’s not surprising, since project attributes are precisely the rules used to ma...

562 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you