Display subtasks in a backlog

Sergey Shmarkatyuk
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 9, 2012

How could I configure GreenHopper to display subtasks in the backlog/sprint and to be able to edit estimates?

Is it possilbe to calculate parent issue estimate (story points) based on subtasks estimates?

1 answer

1 accepted

1 vote
Answer accepted
sclowes
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 10, 2012

The subtasks do not display in the backlog directly, they are shown in the Sub-Tasks tab on the detail view that appears when you click on the issue. You can see what the tab looks like in a screenshot from the release notes.

You can enter the estimate for the sub tasks when you create it from the sub-tasks tab.

There is currently no way to roll up a story point estimate to the parent issue. For more discussion about estimation you might like to check out an answers post on the topic.

Thanks,
Shaun