Different sprints for different Agile boards, doesn't seem to be working?

My JIRA is split into two different projects, and each one has its own Agile board.  Because they sometimes work on different schedules and have different organizational needs, it's important that each board/project has its own sprints.  

This was previously working before the recent changes to Agile, but now it seems that sprints are shared across boards/projects.  Oddly it seems that SOME are shared, and SOME aren't. 

Why is this, and can someone link me to a more thorough explanation of how this works?  

1 answer

0 vote

A Sprint appears in a board if the board shares some of the data with another board on which the Sprint was originally created. When I say the data is shared, it could be because the filter of the board pulls in data from the other project. Is that the case here?

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Sarah Schuster
Posted Mar 28, 2018 in Jira Software

Can a company’s culture make or break agile adoption?

Can a new-to-agile team survive and thrive in a non-agile culture? If so, what advice would you give to those trying to be agile in a non-agile culture? What's the key(s) to success? Share your thoug...

12,063 views 15 13
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you