We are trying to use Jira Cloud to project when a project milestone will be finished. We are looking at the Version Report reports. (BTW, we are running 2-week sprints)
The version report shows our predicted completion date as 7/14/22. However, we predicted we'll finish mid- to late December.
Some additional information:
* 5.06% of the version is unestimated.
* We have 644 points incomplete.
* Our 4-sprint average velocity is 55.25.
Just using those numbers, we can estimate our completion date late September. However, we have some dependencies and limited skill availability, so it got pushed to December. But why is there such a difference between what Jira estimates and what we estimate.
Additionally, I've never seen a burn-up chart go up sharply from today's date like this one..
Any insight is appreciated it. TIA!
It's because you have not given Jira all the data it needs to be able to make the predictions. It has no way of predicting what might happen with the 5% of your un-estimated issues, or your dependencies and skill availability.
It's also an Agile tool, so it assumes there's a lot of change will come into play during each sprint. And you've got up-and-down spikes (lots of re-opening stories after they're done) which suggests you're reporting is likely to be undpredictable.
👋 Hi there Jira Community! A few months ago we shared with you plans around renaming epics in your company-managed projects. As part of these changes, we highlighted upcoming changes to epics on...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.