Hi
I want a cumulative flow chart for a team for the current Sprint only ( or just one sprint)
I want to see how many open issues ( except Epics) entered the Sprint at the beginning of the sprint and then the status of those issues at the end of sprint. I want to see this in the total story points.
Example below:
At the beginning of the sprint:
To Do - 12 Stories - 40 pts
In-Progress - 2 Stories - 6 Pts
Total 46 Pts ( 14 stories)
At the end of Sprint:
To Do - 3 Stories - 9 Pts
In Progress - 0 Stories - 0 Pts
Done - 11 Stories - 37 Pts
Total 46 Pts ( 14 stories) Note: No stories were added/removed during the Sprint.
Can I see the above data in a chart just for one sprint?
At the end of the Sprint Above gives me a completion ratio of 37/46 = 80%
In the chart I should be able to see how the status of the stories changed over the 2 week Sprint duration.