I'm trying to create a nofication that will altert all project members at the end of week to create the next's week sprint.
Is that possible? The only way that i found is to notifiy the user when he end's his week sprint
Thanks
Hi Tiago,
This is not possible in Jira Agile.
As a scrum master I would solve this by notifying the team during the daily standup and help them prepare for the next sprint.
I don't think this is an issue you should solve using tools, solve it using your team.
Best regards,
Peter
How about a cron job in Outlook :-)