I am running into the problem of every ticket involved in a current sprint being moved to the next sprint because the case is not marked as "Resolved", just in the workflow status as "Completed". What is the process of changing an issue to "Resolved" so that there won't be the same cases added into the next sprint, just within the completed section.

 

This is the message that I receive when I try to finish a sprint.

 

Annotation 2019-03-11 091134.jpg

1 answer

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 22, 2019

A task on the scrum board is considered as done or completed only when it reaches the last column on the board. Make sure your statuses are appropriately mapped to the columns on the board.

Looks like your "Completed" status is not mapped to the last column on the board.

Cooper Meredith March 25, 2019

Thank you so much! This solved everything!